AI-powered · Free · No account needed

Free Formwork ITP Generator

Generate a complete Inspection & Test Plan for formwork and falsework in seconds. Covers shoring and propping checks, dimension verification, joint sealing, release agent application, and stripping schedules — with hold points for pre-pour formwork sign-off.

  • Formwork-specific hold points and witness points
  • Aligned with relevant Australian Standards
  • PDF emailed to you instantly — no login required
  • Ready to use on-site or submit to your principal contractor
Describe scope
Review ITP
Get PDF
Done

Include trade, materials, key activities, and any relevant standards (e.g. AS 3600). More detail = better ITP.

No account required. Takes about 10 seconds.

Background

What is a Formwork ITP?

A formwork ITP covers the inspection and testing requirements for temporary structures used to support concrete during placement and curing. It defines what gets inspected at each stage — from foundation and shoring installation through to pre-pour sign-off and stripping.

Formwork failures can have catastrophic consequences. Collapse during pouring has caused fatalities on construction sites. A rigorous ITP with enforced hold points is not just a quality document — it's a critical safety control. The document ensures that shoring capacity, bracing, and connections are all verified before concrete placement.

In Australia, formwork ITPs reference AS 3610 (Formwork for Concrete) and any engineer's formwork design drawings. The formwork contractor must demonstrate that the as-built installation matches the design at the pre-pour hold point.

Quality checkpoints

Formwork ITP Hold Points & Witness Points

The AI generator automatically includes these checkpoints based on your scope description. Hold points require mandatory sign-off before work proceeds; witness points notify the relevant party but don't stop work.

Hold Points

Work stops until signed off

  • Shoring and propping installation inspection
  • Pre-pour formwork inspection (dimensions, levels, bracing)
  • Stripping schedule approval (minimum curing period met)

Witness Points

Party notified, work can continue

  • Foundation and sole plate installation
  • Formwork joint sealing and release agent application
  • Post-strip element condition assessment
  • Backpropping installation for multi-level pours

Applicable Australian Standards

  • AS 3610 — Formwork for Concrete
  • AS 3600 — Concrete Structures

Common questions

Formwork ITP — Frequently Asked Questions

What is the most critical hold point for formwork?
Pre-pour formwork inspection is the most critical hold point. This confirms that dimensions, levels, bracing, and shoring capacity all match the engineer's design before concrete is placed. Once concrete is poured, formwork defects result in either costly remediation or structural non-compliance. This inspection must be signed off by a competent person before the pour can proceed.
When can formwork be stripped?
Stripping schedules depend on the structural element, concrete strength gain, and ambient temperature. AS 3600 provides minimum stripping times, but the project specification may impose longer periods. The ITP should include a hold point or witness point at stripping to verify that the minimum curing period has been met and the concrete has reached the required strength (often verified by test cylinders).
Does the formwork ITP need to cover falsework separately?
Falsework (temporary support structures for elevated formwork) should be included in the formwork ITP as a specific section with its own hold points. Falsework has additional requirements for foundation bearing capacity, bracing, and load path verification that aren't covered by standard ground-level formwork inspection.

Need to manage ITPs across a live project?

The free generator builds a single ITP. HoldPoint gives you the full workflow — templates, digital sign-offs, photo attachments, audit trails, and automatic PDF generation for every document on every project.

14 days free. No credit card to start.