Planter Box Waterproofing Inspection & Test Plan

ITP for planter box waterproofing on podium and rooftop structures covering internal lining, root barriers, drainage layers, overflow provisions and long-term maintenance considerations.

12 checklist items
2 hold points
1 witness points
Use this template, it's free

Used on live Australian projects

DynafixTreu Construct
Read their stories

Checklist Preview

Substrate Preparation

Requires sign-off
P/F
Concrete fully cured and surface prepared
P/F
Internal corner fillets installed
P/F
Drain outlet pre-formed and prepped

Waterproof Lining

Requires sign-off
P/F
Membrane system rated for permanent immersion
Hold
P/F
Membrane continuous to top of planter wall
P/F
Reinforcing band at all corners and junctions
Photo
P/F
Root barrier layer installed over membrane

Drainage & Testing

Requires sign-off
P/F
Drainage cell layer installed at base
P/F
Geotextile filter layer over drainage cells
P/F
Overflow outlet at correct height
P/F
Flood test satisfactory (48-hour minimum)
Hold Witness
P/F
Inspection access for drain maintenance noted

Prefer AI?

Generate a custom Waterproofing ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.

Free AI ITP Generator →

Also free from the HoldPoint QA team: a waterproofing supplier price list template (Excel), to check supplier invoices against with CostCode.

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.

Get started free