All templates
WaterproofingCommercial

Basement Waterproofing Inspection & Test Plan

ITP for below-ground basement waterproofing systems covering external membranes, waterstop installation, tanking systems, drainage boards and joint treatment per AS 3735.

12 checklist items
2 hold points
1 witness points
Use this template — it's free

Checklist Preview

External Membrane

Requires sign-off
P/F
Concrete substrate ground smooth and clean
P/F
Membrane applied per manufacturer specification
P/F
Membrane lap widths per specification
P/F
Protection board installed over membrane
HoldPhoto

Waterstop & Joint Treatment

Requires sign-off
P/F
Waterstop positioned at construction joints
Hold Witness
P/F
Waterstop continuous with welded joints
P/F
Re-injectable grout tubes installed at joints
P/F
Joint sealant applied where specified

Drainage & Completion

Requires sign-off
P/F
Drainage dimple board installed
P/F
Subsoil drain connected to stormwater
P/F
Backfill placed without membrane damage
Post-backfill leak monitoring period commenced

Prefer AI?

Generate a custom Waterproofing ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.

Free AI ITP Generator →

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.

Get started free