WaterproofingResidential
Balcony Waterproofing Inspection & Test Plan
ITP for external balcony waterproofing covering falls verification, membrane system application, upstand details, drainage points and hob construction per AS 4654.2.
12 checklist items
3 hold points
1 witness points
Checklist Preview
Falls & Substrate
Requires sign-offP/F
Falls to drainage outlet verified (min 1:100) Hold
P/F
Substrate moisture content below limitP/F
Hob at door threshold per AS 4654.2 Hold
#
Hob height (mm)Membrane System
Requires sign-offP/F
Membrane system suitable for external exposureP/F
Upstand height minimum 150mm above FFLP/F
Drip edge detail at balcony perimeterP/F
Reinforcement fabric embedded in membranePhoto
Drainage & Testing
Requires sign-offP/F
Outlet puddle flange clamped and sealedP/F
Overflow provision installedP/F
Flood test satisfactory (24-hour minimum) Hold Witness
P/F
Protection board installed before tilingPrefer AI?
Generate a custom Waterproofing ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a waterproofing supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free