Structural Welding Inspection & Test Plan

Dedicated welding ITP for structural steel covering welder qualifications, WPS compliance, preheat requirements, visual inspection and non-destructive testing per AS/NZS 1554.

14 checklist items
3 hold points
2 witness points
Use this template, it's free

Used on live Australian projects

DynafixTreu Construct
Read their stories

Checklist Preview

Pre-Weld Checks

Requires sign-off
P/F
Welder qualifications current for joint category
Hold
P/F
Approved WPS available at workface
P/F
Joint preparation per WPS (bevel, root gap)
P/F
Preheat temperature achieved
Witness
#
Measured preheat temperature (°C)
P/F
Welding consumables per WPS (type and storage)

During Welding

P/F
Interpass temperature within limits
P/F
Run sequence per WPS
P/F
Back gouging where required

Post-Weld Inspection

Requires sign-off
P/F
Visual inspection per AS/NZS 1554 Table 8.1
Hold
P/F
Weld profile within acceptance criteria
P/F
Undercut within permissible limits
P/F
NDT (UT/MT/PT) results satisfactory
Hold Witness
Aa
NDT report reference number

Prefer AI?

Generate a custom Structural Steel ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.

Free AI ITP Generator →

Also free from the HoldPoint QA team: a structural steel supplier price list template (Excel), to check supplier invoices against with CostCode.

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.

Get started free