PlumbingResidential
Plumbing Rough-In Inspection & Test Plan
First-fix plumbing ITP covering water supply pipework, waste and vent piping, fixture point locations and pressure testing prior to concealment. Ensures compliance with AS/NZS 3500.
14 checklist items
2 hold points
1 witness points
Checklist Preview
Water Supply Pipework
Requires sign-offP/F
Pipe material and grade per specificationP/F
Pipe support spacing compliantP/F
Hot water pipe insulation installedP/F
Pressure test at 1500kPa for 30 minutes Hold Witness
P/F
Backflow prevention devices installedWaste & Vent Piping
Requires sign-offP/F
Pipe falls per AS/NZS 3500.2 (1:40 min)P/F
Traps installed at all fixture pointsP/F
Vent pipe termination height compliantP/F
Air admittance valves where permittedP/F
Drain tested with water to full bore Hold
Fixture Point Positions
P/F
Basin rough-in heights per drawingP/F
Toilet set-out dimensions verifiedP/F
Shower waste position correctP/F
Hose cock positions per specificationPrefer AI?
Generate a custom Plumbing ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a plumbing supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free
