Plumbing Rough-In Inspection & Test Plan

First-fix plumbing ITP covering water supply pipework, waste and vent piping, fixture point locations and pressure testing prior to concealment. Ensures compliance with AS/NZS 3500.

14 checklist items
2 hold points
1 witness points
Use this template — it's free

Checklist Preview

Water Supply Pipework

Requires sign-off
P/F
Pipe material and grade per specification
P/F
Pipe support spacing compliant
P/F
Hot water pipe insulation installed
P/F
Pressure test at 1500kPa for 30 minutes
Hold Witness
P/F
Backflow prevention devices installed

Waste & Vent Piping

Requires sign-off
P/F
Pipe falls per AS/NZS 3500.2 (1:40 min)
P/F
Traps installed at all fixture points
P/F
Vent pipe termination height compliant
P/F
Air admittance valves where permitted
P/F
Drain tested with water to full bore
Hold

Fixture Point Positions

P/F
Basin rough-in heights per drawing
P/F
Toilet set-out dimensions verified
P/F
Shower waste position correct
P/F
Hose cock positions per specification

Prefer AI?

Generate a custom Plumbing ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.

Free AI ITP Generator →

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.

Get started free