Fire Hydrant & Hose Reel Plumbing Inspection & Test Plan

ITP for fire hydrant and hose reel pipework installation covering pipe materials, supports, hydrostatic testing, valve installation and flow testing per AS 2419.1.

11 checklist items
3 hold points
2 witness points
Use this template, it's free

Used on live Australian projects

DynafixTreu Construct
Read their stories

Checklist Preview

Pipework Installation

Requires sign-off
P/F
Pipe material per AS 2419.1
P/F
Pipe supports and seismic bracing installed
P/F
Isolation valves at specified locations
P/F
Fire-rated penetration sealing complete
HoldPhoto

Hydrostatic Testing

Requires sign-off
P/F
Hydrostatic test at 1400kPa for 2 hours
Hold Witness
P/F
No leaks observed during test
Aa
Test certificate reference

Flow Testing & Commissioning

Requires sign-off
P/F
Hydrant flow rate meets design requirement
Hold Witness
P/F
Hose reels fully operational
P/F
Brigade booster connection accessible
✓
Block plan installed at hydrant booster

Prefer AI?

Generate a custom Plumbing ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.

Free AI ITP Generator →

Also free from the HoldPoint QA team: a plumbing supplier price list template (Excel), to check supplier invoices against with CostCode.

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.

Get started free