Fire Hydrant & Hose Reel Plumbing Inspection & Test Plan

ITP for fire hydrant and hose reel pipework installation covering pipe materials, supports, hydrostatic testing, valve installation and flow testing per AS 2419.1.

11 checklist items
3 hold points
2 witness points
Use this template — it's free

Checklist Preview

Pipework Installation

Requires sign-off
P/F
Pipe material per AS 2419.1
P/F
Pipe supports and seismic bracing installed
P/F
Isolation valves at specified locations
P/F
Fire-rated penetration sealing complete
HoldPhoto

Hydrostatic Testing

Requires sign-off
P/F
Hydrostatic test at 1400kPa for 2 hours
Hold Witness
P/F
No leaks observed during test
Aa
Test certificate reference

Flow Testing & Commissioning

Requires sign-off
P/F
Hydrant flow rate meets design requirement
Hold Witness
P/F
Hose reels fully operational
P/F
Brigade booster connection accessible
Block plan installed at hydrant booster

Prefer AI?

Generate a custom Plumbing ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.

Free AI ITP Generator →

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.

Get started free