Fire Hydrant & Hose Reel Plumbing Inspection & Test Plan
ITP for fire hydrant and hose reel pipework installation covering pipe materials, supports, hydrostatic testing, valve installation and flow testing per AS 2419.1.
11 checklist items
3 hold points
2 witness points
Checklist Preview
Pipework Installation
Requires sign-offP/F
Pipe material per AS 2419.1P/F
Pipe supports and seismic bracing installedP/F
Isolation valves at specified locationsP/F
Fire-rated penetration sealing complete HoldPhoto
Hydrostatic Testing
Requires sign-offP/F
Hydrostatic test at 1400kPa for 2 hours Hold Witness
P/F
No leaks observed during testAa
Test certificate referenceFlow Testing & Commissioning
Requires sign-offP/F
Hydrant flow rate meets design requirement Hold Witness
P/F
Hose reels fully operationalP/F
Brigade booster connection accessible✓
Block plan installed at hydrant boosterPrefer AI?
Generate a custom Plumbing ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a plumbing supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free