Fire Hydrant & Hose Reel Plumbing Inspection & Test Plan
ITP for fire hydrant and hose reel pipework installation covering pipe materials, supports, hydrostatic testing, valve installation and flow testing per AS 2419.1.
11 checklist items
3 hold points
2 witness points
Checklist Preview
Pipework Installation
Requires sign-offP/F
Pipe material per AS 2419.1P/F
Pipe supports and seismic bracing installedP/F
Isolation valves at specified locationsP/F
Fire-rated penetration sealing complete HoldPhoto
Hydrostatic Testing
Requires sign-offP/F
Hydrostatic test at 1400kPa for 2 hours Hold Witness
P/F
No leaks observed during testAa
Test certificate referenceFlow Testing & Commissioning
Requires sign-offP/F
Hydrant flow rate meets design requirement Hold Witness
P/F
Hose reels fully operationalP/F
Brigade booster connection accessible✓
Block plan installed at hydrant boosterReady to use this template?