Below-Ground Drainage Inspection & Test Plan
ITP for below-ground sanitary and stormwater drainage including bedding preparation, pipe laying, jointing, grade verification and mandrel testing prior to backfill per AS/NZS 3500.2.
13 checklist items
2 hold points
1 witness points
Checklist Preview
Trench & Bedding
Requires sign-offP/F
Trench width and depth per specificationP/F
Bedding material type and compaction#
Bedding thickness (mm)P/F
Subgrade free of rock and debrisPipe Installation
Requires sign-offP/F
Pipe grade verified with laser/level Hold Witness
P/F
Joint assembly per manufacturer instructionsP/F
Junctions and bends at correct locationsP/F
Inspection openings per AS/NZS 3500Testing & Backfill
Requires sign-offP/F
Mandrel test passed (95% nominal ID) Hold
P/F
Water tightness test satisfactoryP/F
CCTV inspection completed (if specified)P/F
Backfill material and compaction compliant✓
Underground marker tape installedPrefer AI?
Generate a custom Plumbing ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a plumbing supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free