VRF / Split System Installation Inspection & Test Plan

ITP for variable refrigerant flow and split system air conditioning covering indoor/outdoor unit mounting, refrigerant piping, condensate drainage, electrical connections and commissioning.

14 checklist items
2 hold points
1 witness points
Use this template — it's free

Checklist Preview

Outdoor Unit

Requires sign-off
P/F
Outdoor unit position per design and noise limits
P/F
Structural support adequate for unit weight
P/F
Vibration isolation mounts installed
P/F
Manufacturer clearances maintained for airflow

Indoor Units

Requires sign-off
P/F
Indoor unit positions per mechanical drawings
P/F
Mounting brackets secure and level
P/F
Condensate drain graded and connected
P/F
Condensate pump installed where gravity drain not possible
P/F
Access provided for maintenance (concealed units)

Commissioning

Requires sign-off
P/F
Refrigerant charge per manufacturer calculation
Hold
P/F
VRF addressing and network setup complete
P/F
Cooling and heating operation verified
Hold Witness
P/F
Room controllers and schedules programmed
P/F
Refrigerant leak detection satisfactory

Ready to use this template?