VRF / Split System Installation Inspection & Test Plan
ITP for variable refrigerant flow and split system air conditioning covering indoor/outdoor unit mounting, refrigerant piping, condensate drainage, electrical connections and commissioning.
14 checklist items
2 hold points
1 witness points
Checklist Preview
Outdoor Unit
Requires sign-offP/F
Outdoor unit position per design and noise limitsP/F
Structural support adequate for unit weightP/F
Vibration isolation mounts installedP/F
Manufacturer clearances maintained for airflowIndoor Units
Requires sign-offP/F
Indoor unit positions per mechanical drawingsP/F
Mounting brackets secure and levelP/F
Condensate drain graded and connectedP/F
Condensate pump installed where gravity drain not possibleP/F
Access provided for maintenance (concealed units)Commissioning
Requires sign-offP/F
Refrigerant charge per manufacturer calculation Hold
P/F
VRF addressing and network setup completeP/F
Cooling and heating operation verified Hold Witness
P/F
Room controllers and schedules programmedP/F