HVACCommercial
Refrigeration Piping Inspection & Test Plan
ITP for refrigerant piping systems covering copper pipe brazing, nitrogen pressure testing, pipe insulation, oil traps and line sizing verification for VRF and split systems per AS/NZS 5149.
12 checklist items
2 hold points
2 witness points
Checklist Preview
Pipe Installation
Requires sign-offP/F
Pipe sizing per manufacturer line sizing chartsP/F
Pipe support spacing per copper tube guidelinesP/F
Pipe ends sealed and nitrogen purge during brazing Hold
P/F
Oil traps provided at vertical risersP/F
Suction line slope back to compressorBrazing Quality
Requires sign-offP/F
Visual inspection of braze joints satisfactoryP/F
Nitrogen purge confirmed during brazing Witness
P/F
All joints accessible for inspectionPressure Testing & Insulation
Requires sign-offP/F
Nitrogen pressure test at design pressure for 24hrs Hold Witness
#
Test pressure (kPa)P/F
Insulation thickness per specificationP/F
Insulation joints sealed and vapour-tightPrefer AI?
Generate a custom HVAC ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a mechanical (HVAC) supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free