HVAC System Commissioning Inspection & Test Plan

ITP for final HVAC commissioning covering air and water balancing, temperature control verification, noise measurements, performance validation and handover documentation per AIRAH guidelines.

13 checklist items
2 hold points
2 witness points
Use this template, it's free

Used on live Australian projects

DynafixTreu Construct
Read their stories

Checklist Preview

Air Side Balancing

Requires sign-off
P/F
Supply air volumes within ±10% of design
Hold
P/F
Return and exhaust air balanced
P/F
Outside air minimum per AS 1668.2
P/F
Diffuser throw and velocity per selection

Water Side Balancing

Requires sign-off
P/F
Chilled water flow rates per design
P/F
Condenser water flow rates per design
P/F
Pump head and flow at duty point
Witness
P/F
Balancing valve settings recorded

Performance Validation

Requires sign-off
P/F
Room temperatures within design band
Hold Witness
P/F
Humidity control within specification
P/F
Noise levels within NC rating
Aa
TAB report reference number
P/F
Outstanding defects listed for rectification

Prefer AI?

Generate a custom HVAC ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.

Free AI ITP Generator →

Also free from the HoldPoint QA team: a mechanical (HVAC) supplier price list template (Excel), to check supplier invoices against with CostCode.

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.

Get started free