Chiller Plant Installation Inspection & Test Plan
ITP for chiller plant and associated systems covering equipment positioning, piping connections, electrical supply, vibration isolation, refrigerant charge and performance testing.
14 checklist items
2 hold points
1 witness points
Checklist Preview
Equipment Positioning
Requires sign-offP/F
Chiller positioned per mechanical drawingsP/F
Structural support and pads adequateP/F
Vibration isolators installed and levelledP/F
Tube pull and maintenance clearances providedPiping & Electrical
Requires sign-offP/F
Chilled water piping connected and flushedP/F
Condenser water piping connectedP/F
Flexible connections at chiller inlet/outletP/F
Electrical supply per chiller nameplate Hold
P/F
VSD configured per manufacturer settingsCommissioning
Requires sign-offP/F
Refrigerant charge verifiedP/F
Oil charge level per manufacturer specP/F
Performance test at design conditions Hold Witness
P/F
All safety cutouts tested and verifiedP/F
BMS integration and alarm points verifiedReady to use this template?