GlazingCommercial
Curtain Wall Glazing Inspection & Test Plan
ITP for curtain wall façade systems covering mullion installation, transom alignment, glass unit installation, structural silicone application and weather seal testing per AS 2047.
13 checklist items
3 hold points
2 witness points
Checklist Preview
Framing Installation
Requires sign-offP/F
Mullion alignment plumb within tolerance Hold
P/F
Transom levels per designP/F
Bracket and anchor fixings per structural designP/F
Thermal break continuity maintainedP/F
Movement allowance per structural engineerGlazing Installation
Requires sign-offP/F
Glass type and make-up per specification Hold
P/F
Glass seated on setting blocksP/F
Structural silicone applied per manufacturer spec Witness
P/F
Pressure plates and caps installedSealing & Testing
Requires sign-offP/F
Perimeter weather seals installedP/F
Drainage and weep slots clearP/F
Hose water test satisfactory per AS 2047 Hold Witness
P/F
No visible distortion or coating defectsPrefer AI?
Generate a custom Glazing ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a glazing supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free