Checklist Preview

Mould Fabrication

Requires sign-off
P/F
Mould dimensions per production drawings
Hold
P/F
Mould surface finish suitable for required class
P/F
Side rails or magnetic formwork aligned

Pre-Pour

Requires sign-off
P/F
Release agent uniformly applied
P/F
Cast-in inserts positioned per drawing
Hold Witness
P/F
Lifting anchors at correct position and depth
P/F
Reinforcement cover verified with spacers

Demoulding & Handling

Requires sign-off
P/F
Minimum demoulding strength achieved
Hold
P/F
Demoulding procedure followed without damage
P/F
Element marked with ID and orientation
P/F
Stored on appropriate dunnage and supports

Prefer AI?

Generate a custom Formwork ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.

Free AI ITP Generator →

Also free from the HoldPoint QA team: a formwork supplier price list template (Excel), to check supplier invoices against with CostCode.

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.

Get started free