Post-Tensioned Slab Formwork Inspection & Test Plan
ITP for formwork systems supporting post-tensioned concrete slabs covering design for PT loads, stressing end clearances, strand deflection support and re-propping after stressing per AS 3610.
12 checklist items
3 hold points
1 witness points
Checklist Preview
Design for PT Loads
Requires sign-offP/F
Formwork design accounts for PT loading Hold
P/F
Stressing end pocket formwork positionedP/F
Strand deflection support chairs at correct spacingP/F
Dead end anchorage blockouts formedErection
Requires sign-offP/F
Soffit level set with camber per engineerP/F
Prop load capacity verified for PT slab weight Hold
P/F
Edge forms allow stressing jack accessP/F
Pour strip formwork installed where specifiedStripping & Re-propping
Requires sign-offP/F
Stressing completed before strip approval Hold Witness
P/F
Strip sequence per engineer instructionP/F
Re-propping installed per structural requirementsP/F
Re-propping duration per engineer specificationPrefer AI?
Generate a custom Formwork ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a formwork supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free