Insulated Concrete Formwork (ICF) Inspection & Test Plan
ITP for insulated concrete formwork systems covering block assembly, bracing, reinforcement placement within ICF cores, concrete pour rate management and thermal performance verification.
12 checklist items
3 hold points
1 witness points
Checklist Preview
ICF Block Assembly
Requires sign-offP/F
ICF block type and size per designP/F
Wall alignment plumb and straightP/F
Corner and junction details per manufacturerP/F
Openings framed with lintel reinforcementBracing & Reinforcement
Requires sign-offP/F
Bracing system installed per manufacturer spec Hold
P/F
Vertical and horizontal reinforcement placed Hold Witness
P/F
Reinforcement lap lengths per structural designP/F
Services conduits placed within coresConcrete Pour
Requires sign-offP/F
Concrete mix design suitable for ICF (max 20mm agg)P/F
Pour rate within ICF pressure limits Hold
P/F
Internal vibration per manufacturer guidelinesP/F
Wall monitored for blowouts during pourReady to use this template?