Fire ProtectionCommercial
Fire Sprinkler System Inspection & Test Plan
ITP for automatic fire sprinkler systems covering pipework installation, head placement, hydraulic testing, alarm valve operation and system commissioning per AS 2118.
13 checklist items
2 hold points
2 witness points
Checklist Preview
Pipework Installation
Requires sign-offP/F
Pipe material and class per specificationP/F
Pipe hanger spacing per AS 2118P/F
Seismic bracing installed per NZS 4219P/F
Branch line spacing per designSprinkler Heads
Requires sign-offP/F
Head type and temperature rating correct Hold
P/F
Deflector-to-ceiling distance per AS 2118P/F
Head coverage area within maximum spacingP/F
Obstruction clearance rules satisfiedTesting & Commissioning
Requires sign-offP/F
Hydrostatic test at 1400kPa for 2 hours Hold Witness
P/F
Alarm valve operation satisfactoryP/F
Flow switch activating fire panel Witness
P/F
Main drain test flow satisfactory✓
Block plan installed at alarm valvePrefer AI?
Generate a custom Fire Protection ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a fire protection supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free
