Fire Hydrant System Inspection & Test Plan

ITP for building fire hydrant systems covering pipework, hydrant valve installation, booster assembly, flow and pressure testing per AS 2419.1 and authority requirements.

12 checklist items
3 hold points
2 witness points
Use this template, it's free

Used on live Australian projects

DynafixTreu Construct
Read their stories

Checklist Preview

Pipework

Requires sign-off
P/F
Pipe material and rating per AS 2419.1
P/F
Pipe routing per hydraulic design
P/F
Isolation valves at required locations
P/F
Fire-rated penetration sealing
Hold

Hydrant Valves & Landing Valves

Requires sign-off
P/F
Hydrant valve height per AS 2419.1
P/F
Hydrant signage and marking installed
P/F
Landing valves accessible in stair pressurisation zone

Booster Assembly & Testing

Requires sign-off
P/F
Booster assembly per AS 2419.1 detail
Hold
P/F
Hydrostatic test satisfactory
Hold Witness
P/F
Flow and pressure test at most remote hydrant
Witness
P/F
Fire brigade connection approved
✓
System block plan installed at booster

Prefer AI?

Generate a custom Fire Protection ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.

Free AI ITP Generator →

Also free from the HoldPoint QA team: a fire protection supplier price list template (Excel), to check supplier invoices against with CostCode.

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.

Get started free