Fire ProtectionCommercial
Fire Hydrant System Inspection & Test Plan
ITP for building fire hydrant systems covering pipework, hydrant valve installation, booster assembly, flow and pressure testing per AS 2419.1 and authority requirements.
12 checklist items
3 hold points
2 witness points
Checklist Preview
Pipework
Requires sign-offP/F
Pipe material and rating per AS 2419.1P/F
Pipe routing per hydraulic designP/F
Isolation valves at required locationsP/F
Fire-rated penetration sealing Hold
Hydrant Valves & Landing Valves
Requires sign-offP/F
Hydrant valve height per AS 2419.1P/F
Hydrant signage and marking installedP/F
Landing valves accessible in stair pressurisation zoneBooster Assembly & Testing
Requires sign-offP/F
Booster assembly per AS 2419.1 detail Hold
P/F
Hydrostatic test satisfactory Hold Witness
P/F
Flow and pressure test at most remote hydrant Witness
P/F
Fire brigade connection approved✓
System block plan installed at boosterPrefer AI?
Generate a custom Fire Protection ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a fire protection supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free