Shoring & Retention System Inspection & Test Plan

ITP for temporary shoring and earth retention systems covering sheet piling, soldier pile walls, shotcrete, ground anchors and deflection monitoring for deep excavations.

13 checklist items
3 hold points
2 witness points
Use this template, it's free

Used on live Australian projects

DynafixTreu Construct
Read their stories

Checklist Preview

Design & Documentation

Requires sign-off
P/F
Shoring design certified by geotechnical engineer
Hold
P/F
Construction sequence plan reviewed
P/F
Monitoring plan established

Installation

Requires sign-off
P/F
Piles installed to design depth and alignment
Hold Witness
P/F
Walers and struts installed per staging plan
P/F
Shotcrete thickness and mix per specification
P/F
Ground anchors installed and proof-tested
Hold
#
Anchor proof test load (kN)

Monitoring & Performance

Requires sign-off
P/F
Inclinometer readings within design limits
P/F
Survey monitoring of adjacent structures
Witness
P/F
Groundwater level below formation
#
Maximum wall deflection (mm)
P/F
Trigger levels reviewed and current

Prefer AI?

Generate a custom Excavation ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.

Free AI ITP Generator →

Also free from the HoldPoint QA team: a civil and earthworks supplier price list template (Excel), to check supplier invoices against with CostCode.

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.

Get started free