Dewatering Inspection & Test Plan

ITP for construction dewatering covering pump selection, discharge management, drawdown monitoring, settlement monitoring and environmental compliance for groundwater management.

12 checklist items
3 hold points
2 witness points
Use this template — it's free

Checklist Preview

Dewatering Design

Requires sign-off
P/F
Dewatering plan reviewed and approved
Hold
P/F
Pump capacity adequate for estimated inflow
P/F
Discharge location and approval obtained
Environmental licence in place (if required)

Installation & Operation

Requires sign-off
P/F
Wellpoint or sump spacing per design
P/F
Standby pump installed and operational
P/F
Discharge water quality within limits
Witness
P/F
Sediment control at discharge point

Monitoring

Requires sign-off
P/F
Drawdown level maintained below formation
Hold
P/F
Piezometer readings recorded regularly
P/F
Settlement monitoring of adjacent structures
Hold Witness
#
Pump flow rate (L/s)

Ready to use this template?

Sign up for free, import this ITP template into your project, and start inspecting. Your first project is always free.