Switchboard Installation Inspection & Test Plan
Comprehensive ITP for main and distribution switchboard installation including bus-bar connections, circuit breaker coordination, arc fault containment and labelling compliance per AS/NZS 3000 and AS/NZS 61439.
16 checklist items
3 hold points
1 witness points
Checklist Preview
Physical Installation
Requires sign-offP/F
Switchboard mounting plumb and levelP/F
Seismic restraints installed where requiredP/F
Working clearance zones maintainedP/F
Ventilation clearances per manufacturerP/F
Cable entry glands correctly fittedInternal Wiring & Connections
Requires sign-offP/F
Bus-bar connection torque values verified Hold Witness
P/F
Phase rotation correct (L1-L2-L3) Hold
P/F
Neutral bar connections secureP/F
Internal cable dressing neat and compliantP/F
Arc fault containment rating verifiedProtection & Coordination
Requires sign-offP/F
Protection coordination study reviewed Hold
P/F
CT ratios verified per metering specP/F
Surge protection device installedLabelling & Documentation
P/F
Circuit directory completed and affixedP/F
Danger and warning labels affixed✓
As-built single-line diagram providedPrefer AI?
Generate a custom Electrical ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a electrical supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free