Solar PV System Inspection & Test Plan
Covers rooftop solar photovoltaic installation including panel mounting, DC cabling, inverter installation, grid connection and anti-islanding protection per AS/NZS 5033 and AS 4777.
14 checklist items
3 hold points
1 witness points
Checklist Preview
Panel Mounting
Requires sign-offP/F
Roof structural adequacy confirmed Hold
P/F
Mounting rail fixing torque verifiedP/F
Panel orientation and tilt per designP/F
Panel clamps secure with correct torqueP/F
Boundary and ridge setbacks compliantDC Wiring & Protection
Requires sign-offP/F
DC cables UV-rated and correctly supportedP/F
MC4 connector engagement verified#
String Voc measurementP/F
DC isolator installed at array and inverter Hold
Inverter & Grid Connection
Requires sign-offP/F
Inverter mounted per manufacturer specsP/F
Anti-islanding protection verified Hold Witness
P/F
Export limit configured if requiredP/F
Generation meter installed and reading✓
CER STC assignment form completedPrefer AI?
Generate a custom Electrical ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a electrical supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free