Electrical Fit-Off Inspection & Test Plan
Second-fix electrical inspection covering the installation of accessories, luminaires, switchgear and final circuit testing. Validates compliance prior to energisation and certificate of compliance.
15 checklist items
3 hold points
1 witness points
Checklist Preview
Accessories & Fixtures
Requires sign-offP/F
GPOs installed and correctly orientedP/F
Light switches operating correctlyP/F
Luminaires installed per specificationP/F
Downlight thermal clearances maintainedPhoto
P/F
Data outlets installed and labelledSwitchboard
Requires sign-offP/F
Circuit breaker ratings per design Hold
P/F
RCD protection installed per AS/NZS 3000 Hold
P/F
Circuit directory and labelling completeP/F
Cable terminations torqued to specificationTesting & Commissioning
Requires sign-offP/F
Insulation resistance test (minimum 1MΩ) Hold
P/F
Polarity test satisfactoryP/F
Earth fault loop impedance within limitsP/F
RCD trip time within 300ms Witness
#
Supply voltage within toleranceAa
Certificate of compliance numberPrefer AI?
Generate a custom Electrical ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a electrical supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free