Electrical Fit-Off Inspection & Test Plan
Second-fix electrical inspection covering the installation of accessories, luminaires, switchgear and final circuit testing. Validates compliance prior to energisation and certificate of compliance.
15 checklist items
3 hold points
1 witness points
Checklist Preview
Accessories & Fixtures
Requires sign-offP/F
GPOs installed and correctly orientedP/F
Light switches operating correctlyP/F
Luminaires installed per specificationP/F
Downlight thermal clearances maintainedPhoto
P/F
Data outlets installed and labelledSwitchboard
Requires sign-offP/F
Circuit breaker ratings per design Hold
P/F
RCD protection installed per AS/NZS 3000 Hold
P/F
Circuit directory and labelling completeP/F
Cable terminations torqued to specificationTesting & Commissioning
Requires sign-offP/F
Insulation resistance test (minimum 1MΩ) Hold
P/F
Polarity test satisfactoryP/F
Earth fault loop impedance within limitsP/F
RCD trip time within 300ms Witness
#
Supply voltage within toleranceAa
Certificate of compliance numberPrefer AI?
Generate a custom Electrical ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.
Free AI ITP Generator →Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.
Get started free