ElectricalCommercial
Fire Detection & Alarm System Inspection & Test Plan
Inspection and test plan for fire detection and alarm systems covering detector placement, sounder circuits, MCP positioning, zone wiring and end-of-line monitoring per AS 1670.1.
14 checklist items
3 hold points
3 witness points
Checklist Preview
Detector Installation
Requires sign-offP/F
Detector spacing per AS 1670.1P/F
Detector mounting height compliantP/F
Detector types match design for each zone Witness
P/F
Beam detector alignment verifiedP/F
Duct detectors coordinated with HVACWiring & Circuits
Requires sign-offP/F
Fire-rated cable used where specified Hold
P/F
End-of-line devices installed per zoneP/F
Fire circuits isolated from other servicesP/F
Loop resistance within manufacturer limitsPanel & Commissioning
Requires sign-offP/F
Fire indicator panel programmed per cause-effect Hold Witness
P/F
All sounders audible throughout building Witness
P/F
Manual call points tested and operationalP/F
Fire brigade connection verified Hold
✓
Zone plan affixed adjacent to FIPPrefer AI?
Generate a custom Electrical ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a electrical supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free