Services Disconnection Inspection & Test Plan

ITP for pre-demolition services disconnection covering electrical isolation, gas capping, water disconnection, sewer capping, data removal and authority notifications.

13 checklist items
3 hold points
1 witness points
Use this template, it's free

Used on live Australian projects

DynafixTreu Construct
Read their stories

Checklist Preview

Authority Notifications

Requires sign-off
P/F
Electricity authority disconnection confirmed
Hold
P/F
Gas authority disconnection/capping confirmed
Hold
P/F
Water authority disconnection confirmed
P/F
Telecommunications provider notified and disconnected

Site Isolation

Requires sign-off
P/F
Main switchboard de-energised and locked off
Hold
P/F
Gas meter removed or capped at main
P/F
Water supply capped at boundary
P/F
Sewer connection capped at boundary
P/F
Stormwater connections noted for future work

Verification

Requires sign-off
P/F
Dead test on all electrical circuits
Witness
P/F
Gas line pressure confirmed at zero
✓
All disconnection certificates received
Aa
Service disconnection register reference

Prefer AI?

Generate a custom Demolition ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.

Free AI ITP Generator →

Also free from the HoldPoint QA team: a demolition supplier price list template (Excel), to check supplier invoices against with CostCode.

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.

Get started free