Services Disconnection Inspection & Test Plan

ITP for pre-demolition services disconnection covering electrical isolation, gas capping, water disconnection, sewer capping, data removal and authority notifications.

13 checklist items
3 hold points
1 witness points
Use this template — it's free

Checklist Preview

Authority Notifications

Requires sign-off
P/F
Electricity authority disconnection confirmed
Hold
P/F
Gas authority disconnection/capping confirmed
Hold
P/F
Water authority disconnection confirmed
P/F
Telecommunications provider notified and disconnected

Site Isolation

Requires sign-off
P/F
Main switchboard de-energised and locked off
Hold
P/F
Gas meter removed or capped at main
P/F
Water supply capped at boundary
P/F
Sewer connection capped at boundary
P/F
Stormwater connections noted for future work

Verification

Requires sign-off
P/F
Dead test on all electrical circuits
Witness
P/F
Gas line pressure confirmed at zero
All disconnection certificates received
Aa
Service disconnection register reference