Services Disconnection Inspection & Test Plan
ITP for pre-demolition services disconnection covering electrical isolation, gas capping, water disconnection, sewer capping, data removal and authority notifications.
13 checklist items
3 hold points
1 witness points
Checklist Preview
Authority Notifications
Requires sign-offP/F
Electricity authority disconnection confirmed Hold
P/F
Gas authority disconnection/capping confirmed Hold
P/F
Water authority disconnection confirmedP/F
Telecommunications provider notified and disconnectedSite Isolation
Requires sign-offP/F
Main switchboard de-energised and locked off Hold
P/F
Gas meter removed or capped at mainP/F
Water supply capped at boundaryP/F
Sewer connection capped at boundaryP/F
Stormwater connections noted for future workVerification
Requires sign-offP/F
Dead test on all electrical circuits Witness
P/F
Gas line pressure confirmed at zero✓
All disconnection certificates receivedAa
Service disconnection register referencePrefer AI?
Generate a custom Demolition ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a demolition supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free