Reinforcement Supply & Placement Inspection & Test Plan

Dedicated ITP for steel reinforcement covering material traceability, storage, bending schedules, placement tolerances, mechanical couplers and pre-stressing strand installation per AS 3600.

13 checklist items
3 hold points
2 witness points
Use this template — it's free

Checklist Preview

Material Supply & Storage

Requires sign-off
P/F
Mill certificates received and verified
Hold
P/F
Bar grade identification markings checked
P/F
Reinforcement stored off ground and protected
P/F
No excessive corrosion or contamination

Bending Schedule Verification

Requires sign-off
P/F
Bending schedule matches structural drawings
P/F
Bar dimensions within AS 3600 tolerances
P/F
Minimum bend diameters compliant

Placement & Fixing

Requires sign-off
P/F
Bar placement matches structural drawings
Hold Witness
P/F
Bar spacing within ±10mm tolerance
P/F
Cover blocks at maximum 1m centres
P/F
Mechanical couplers installed per specification
Witness
P/F
Lap splice lengths per design
#
Measured cover depth (mm)
Hold

Prefer AI?

Generate a custom Concrete ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.

Free AI ITP Generator →

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.

Get started free