Tendon Installation
Requires sign-offP/F
Tendon profile per PT drawings Hold
P/F
Tendon spacing compliantP/F
Anchorage hardware correctly installedP/F
Duct integrity verified (no damage)P/F
Anchor zone reinforcement per design Hold
Stressing Operations
Requires sign-offP/F
Minimum concrete strength for stressing achieved Hold Witness
P/F
Jack calibration certificate currentP/F
Stressing sequence per engineer specificationP/F
Elongation within ±7% of calculated Hold
#
Measured elongation (mm)P/F
Lock-off force recordedGrouting (Bonded System)
Requires sign-offP/F
Grout mix design per specificationP/F
Grout injection continuous from low to high point Witness
P/F
Grout cube strength satisfactoryP/F
Anchor pocket filled and sealedPrefer AI?
Generate a custom Concrete ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.
Free AI ITP Generator →Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.
Get started free