ConcreteCommercial
Post-Tensioning Inspection & Test Plan
ITP for bonded and unbonded post-tensioning systems covering tendon profiling, anchor zone reinforcement, stressing operations, elongation checks and grouting per AS 3600.
15 checklist items
4 hold points
2 witness points
Checklist Preview
Tendon Installation
Requires sign-offP/F
Tendon profile per PT drawings Hold
P/F
Tendon spacing compliantP/F
Anchorage hardware correctly installedP/F
Duct integrity verified (no damage)P/F
Anchor zone reinforcement per design Hold
Stressing Operations
Requires sign-offP/F
Minimum concrete strength for stressing achieved Hold Witness
P/F
Jack calibration certificate currentP/F
Stressing sequence per engineer specificationP/F
Elongation within ±7% of calculated Hold
#
Measured elongation (mm)P/F
Lock-off force recordedGrouting (Bonded System)
Requires sign-offP/F
Grout mix design per specificationP/F
Grout injection continuous from low to high point Witness
P/F
Grout cube strength satisfactoryP/F
Anchor pocket filled and sealedPrefer AI?
Generate a custom Concrete ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.
Free AI ITP Generator →Also free from the HoldPoint QA team: a concrete supplier price list template (Excel), to check supplier invoices against with CostCode.
Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.
Get started free