Concrete Post-Pour Inspection & Test Plan

Post-pour inspection ITP covering curing regime, formwork stripping, surface finish assessment, dimensional checks and compressive strength test results per AS 3600.

12 checklist items
3 hold points
1 witness points
Use this template — it's free

Checklist Preview

Curing

Requires sign-off
P/F
Curing method as specified (compound/water/membrane)
P/F
Curing commenced within specified timeframe
Hold
P/F
Minimum curing duration maintained
P/F
Ambient temperature during curing recorded

Formwork Stripping

Requires sign-off
P/F
Minimum stripping strength achieved
Hold Witness
P/F
No damage observed on formwork removal
P/F
Reshoring installed where required

Quality Assessment

Requires sign-off
P/F
Surface finish meets class requirement
P/F
No honeycombing or voids observed
Photo
P/F
Dimensional tolerances within AS 3600 limits
P/F
Crack assessment satisfactory
#
28-day compressive strength result (MPa)