ConcreteCommercial
Concrete Post-Pour Inspection & Test Plan
Post-pour inspection ITP covering curing regime, formwork stripping, surface finish assessment, dimensional checks and compressive strength test results per AS 3600.
12 checklist items
3 hold points
1 witness points
Checklist Preview
Curing
Requires sign-offP/F
Curing method as specified (compound/water/membrane)P/F
Curing commenced within specified timeframe Hold
P/F
Minimum curing duration maintainedP/F
Ambient temperature during curing recordedFormwork Stripping
Requires sign-offP/F
Minimum stripping strength achieved Hold Witness
P/F
No damage observed on formwork removalP/F
Reshoring installed where requiredQuality Assessment
Requires sign-offP/F
Surface finish meets class requirementP/F
No honeycombing or voids observedPhoto
P/F
Dimensional tolerances within AS 3600 limitsP/F
Crack assessment satisfactory#
28-day compressive strength result (MPa) Hold
Ready to use this template?
Sign up for free, import this ITP template into your project, and start inspecting. Your first project is always free.
Get started free