Concrete Post-Pour Inspection & Test Plan

Post-pour inspection ITP covering curing regime, formwork stripping, surface finish assessment, dimensional checks and compressive strength test results per AS 3600.

12 checklist items
3 hold points
1 witness points
Use this template, it's free

Used on live Australian projects

DynafixTreu Construct
Read their stories

Checklist Preview

Curing

Requires sign-off
P/F
Curing method as specified (compound/water/membrane)
P/F
Curing commenced within specified timeframe
Hold
P/F
Minimum curing duration maintained
P/F
Ambient temperature during curing recorded

Formwork Stripping

Requires sign-off
P/F
Minimum stripping strength achieved
Hold Witness
P/F
No damage observed on formwork removal
P/F
Reshoring installed where required

Quality Assessment

Requires sign-off
P/F
Surface finish meets class requirement
P/F
No honeycombing or voids observed
Photo
P/F
Dimensional tolerances within AS 3600 limits
P/F
Crack assessment satisfactory
#
28-day compressive strength result (MPa)
Hold

Prefer AI?

Generate a custom Concrete ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles, tailored to your project.

Free AI ITP Generator →

Also free from the HoldPoint QA team: a concrete supplier price list template (Excel), to check supplier invoices against with CostCode.

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free, no credit card required.

Get started free