ConcreteResidential
Ground Slab Inspection & Test Plan
ITP for residential and commercial ground floor slabs covering subgrade preparation, vapour barrier, reinforcement, joint layout, concrete placement and flatness tolerances per AS 3600 and AS 2870.
13 checklist items
3 hold points
1 witness points
Checklist Preview
Subgrade Preparation
Requires sign-offP/F
Subgrade compacted to 95% MDD Hold
P/F
Fill material per specificationP/F
Termite treatment applied per specificationP/F
Vapour barrier installed and lapped correctlyReinforcement & Joints
Requires sign-offP/F
Reinforcement type and size per structural drawings Hold Witness
P/F
Bar chairs maintaining correct coverP/F
Edge rebate and beam formwork setP/F
Control joint layout per structural designConcrete Placement
Requires sign-offP/F
Concrete grade and slump per specificationP/F
Placement method minimising segregationP/F
Floor flatness/levelness (FF/FL) per specification Hold
P/F
Curing commenced within specified timeframeP/F
Control joints cut within 24 hoursPrefer AI?
Generate a custom Concrete ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.
Free AI ITP Generator →Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.
Get started free