Formwork System Inspection & Test Plan
ITP for formwork system erection covering design certification, prop loading, shore spacing, alignment verification, safety provisions and striking criteria per AS 3610.
13 checklist items
2 hold points
Checklist Preview
Design & Documentation
Requires sign-offP/F
Formwork design certified by engineer Hold
✓
Safe work method statement reviewedP/F
Formwork materials in serviceable conditionErection & Alignment
Requires sign-offP/F
Base plates on adequate bearing surfaceP/F
Shore spacing per formwork drawings Hold
P/F
Props plumb and bracedP/F
Camber provision per engineer specificationP/F
Bearer and joist spacing compliantP/F
Deck sheets free from damage and gapsSafety & Striking
Requires sign-offP/F
Edge protection installed at all open edgesP/F
Safe access provided to all work areasP/F
Striking criteria defined and documented#
Minimum stripping strength requirement (MPa)Ready to use this template?